Kahramaa officials during the opening of Al Bidaa Metro Substation yesterday.
Qatar General Electricity and Water Corporation (Kahramaa) has commissioned Al Bidaa Metro Substation at a cost of QR300m.
With the opening of new project yesterday, all five electricity substations of Kahramaa pertaining to Doha Metro project of Qatar Rail have come to an end. The Al Bidaa Substation of Kahramaa is embedded with multi- story car parking with the capacity of 625 vehicles.
Al Bidaa 33/123 KV Electricity substation is a part of phase 12 of Qatar electricity transmission network expansion project. The substation is fed from Al Suwaidi super by 132 KV cable with the length of 5.4 km. The substation has 132/32 KV transformers, 132/33 KV GIS and other allied equipment. The substation capacity is 100 MVA. Kahramaa President Eng. Essa bin Hilal Al Kuwari said: “We are proud to complete all electricity substations Kahramaa implemented for Qatar Rail to provide Doha Metro Project will all electricity needs.”
Al Kuwari added that Kahramaa gives top priority to Doha Metro substations in project awarding where we manage to accomplish as per the approved timetable and as per highest standards, as the substations for Doha Metro are equipped with special technology to ensure uninterrupted power supply in emergency situations.
The substation building has sixth- story car parking which will be completed soon and will have the space for 625 cars. It is being equipped with the latest safety and security systems followed in Qatar. The main entrance of building and floors’ entrances have been provided with electric display screens, displaying the number of vacant parking lots available at each floor.
This substation is one of kahramaa achievements as a key partner in the development of the projects witnessed by the State, which reflects Kahramaa’s commitment in implementing the infrastructure projects in line with the pursued time schedule.
Kahramaa has commissioned five electricity substations for Qatar Rail to provide Metro Station will all requirements of electricity with total cost of QR900m . Ras Abu Funtas metro substation was commissioned in July 2017 and the second one Lusail Metro electricity substation in March 2018.
Al Waab metro substation was commissioned in June 2018, Doha West metro substation became operational in September 2018. The last substation ‘Al Bidaa Metro’ was commissioned in November 2019.